The N11/M11 Bus Priority Interim Scheme is being implemented in accordance with Transport Infrastructure Ireland’s Project Management Guidelines (PMGs). These guidelines provide a framework for the management, development and delivery of national road and public transport capital projects. The PMGs divide the evolution and progression of a project into an eight-phase process (Phase 0 – 7 inclusive) as listed below:
- Phase 0 – Scope & Pre-Appraisal
- Phase 1 – Concept & Feasibility
- Phase 2 – Option Selection
- Phase 3 – Design & Environmental Evaluation
- Phase 4 – Statutory Processes
- Phase 5 – Enabling & Procurement
- Phase 6 – Construction & Implementation
- Phase 7 – Close Out & Review
Arup has been appointed to progress the delivery of the project through Phases 0 to 4 of the PMGs. Details of the key processes and deliverables within each phase are described under each individual tab above.